Highway 420 and QEW Rehabilitation: Road Closures in Effect June 13 to June 16

Listen to this page

Niagara Falls, ON, June 8, 2016 - The Ontario Ministry of Transportation (MTO) will be rehabilitating 5 structures within the Highway 420/QEW interchange in Niagara Falls, and undertaking resurfacing of Highway 420 from Stanley Avenue to Montrose Road and the Highway 420 interchange including all ramps and crossing roads, over the next two years.

To prepare for this work:

  • Road closures will be in effect from Monday June 13 to Thursday, June 16 11:00pm until 6:00am each day
  • HWY 420 Westbound between Stanley Avenue and Montrose Road

And the following On/Off ramps to and from the HWY 420 Westbound:

  • Dorchester Road/ Lundy’s Lane
  • Drummond Road
  • QEW

During this time period, please use signed detour route(s).

Road and ramp closures will be in effect while the rehabilitation work takes place. We will provide the details regarding these future closures as the information becomes available.

Thank you for your cooperation.

Morrison Hershfield is the MTO’s Contract Administrator for this project.

For more information, contact:

Katherine Kirkpatrick, Principal Contract Administrator, Morrison Hershfield
Phone: 289-434-4297, Email: Hwy420QEW@morrisonhershfield.com 

Posted on: 6/8/2016 16:6 PM - Category: Media Releases