Special Notices

TypeTitleDatesRoad ClosuresDetails
Park and Trail ClosureJohn N. Allan Park10/23/2023 - 5/10/2024Full RoadMore Info
Road ClosureBeck Road at Lyon's Creek12/4/2023 - 7/30/2024Full RoadMore Info
Road ClosureChippawa Parkway - Stanley Avenue to Dorchester Road12/4/2023 - 4/1/2024Full RoadMore Info

Public Notices

  • Notice of Public Meeting - AM-2023-030 - 3958 Cardinal Drive (ZBA & Vacant Land Condominum)

    Description

    A zoning by-law amendment application has been submitted to permit 33 townhouse dwelling units in 5 blocks, Schedule 1 shows the details of the proposal.

    The land is currently zoned Residential Low Density Group Multiple Dwellings (R4-815) in accordance with Zoning By-law 79, 200 as amended by By-law No. 2020-050. The current zoning permits a 118-unit retirement home with height variations from 15.6 m to 19.2 m. The applicant is requesting to place the townhouses under a site-specific Low-Density Group Multiple Dwellings (R4) zone. The proposal includes: a reduction of the minimum lot area for each dwelling unit, a reduction of the minimum front yard depth, a reduction of the minimum rear yard depth, increase in the maximum height of the building and a reduction of the privacy yard depth.

    Digital copies of plans and documents submitted with the application may be obtained on the Planning Department Current Applications webpage.

    Posting Dates

    3/28/2024 to 5/1/2024
  • Notice of Construction - Main Street (Chippawa) Road Reconstruction (Sodom Road to Dock Street)

    Description

    The City of Niagara Falls will be conducting various infrastructure improvements on Main Street Chippawa including new sanitary and storm sewers, full depth road reconstruction, new sidewalks, bicycle lanes, driveways, curbs, and boulevards on;

    Main Street Chippawa (Dock Street to Oliver Street)
    Main Street Chippawa (Oliver Street to Sodom Road)

    This contract will be carried out for the City of Niagara Falls by Baiocco Construction Corp

    At times it may be difficult to drive through the above location due to construction progress. Due to the scope of the work involved, Main Street Chippawa may be limited to one side of pedestrian traffic at times. Driveway accessibility will be affected periodically during sidewalk construction with every effort being made to give advance notice as these restrictions are implemented

    Construction is tentatively scheduled to commence on April 9, 2024, and will be continuous until completion, approximately November 2024 weather and supplies permitting.

    Two lanes of traffic will be maintained whenever possible. Rolling road closures of Main Street Chippawa are expected within the various stages of construction during the sanitary sewer and storm sewer installation. The timing and limits of all road closures will be provided in advance.

    For further information you may contact:              

    Wendy Eitzen, P.Eng.
    Project Manager, Municipal Works
    City of Niagara Falls
    Phone: 905-356-7521, Ext. 4337
    Email: [email protected]

    Posting Dates

    3/26/2024 to 11/30/2024
  • Special Council Meeting - In-Camera

    Description

    Council will hold a Special Meeting of Council during an In-Camera Session, not open to the public.

    Posting Dates

    3/20/2024 to 5/15/2024
  • Notice of Construction - Waters Ave., Ann St. and Richmond Cr. Watermain Replacement

    Description

    The City of Niagara Falls will be completing the watermain replacement and water service replacement, complete with all restorations on;

    Richmond Crescent
    Ann Street (Douglas Crescent to Waters Avenue)
    Waters Avenue (Ann Street to Centennial Street)

    At times it may be difficult to drive through the above location due to construction in progress. In accordance with the contract documents, the contractor, Catalina Excavating Inc. is required to notify the emergency services of their daily operations.

    The work is scheduled to commence on February 1, 2024 and will be continuous until completion, approximately June 2024 weather permitting. Equipment will start arriving on site as early as February 1, 2024.

    It is anticipated that one lane of traffic will be maintained during construction with the exception of planned rolling road closures. The timing and limits of all road closures will be provided in advance.

    For further information you may contact:

    Steven Kizlan, P.Eng.
    Senior Project Manager
    Municipal Works
    City of Niagara Falls
    4310 Queen Street, P.O. Box 1023
    Niagara Falls, ON L2E 6X5
    (905) 356-7521 ext. 4288
    [email protected]

    Attachments

    Posting Dates

    2/1/2024 to 6/30/2024
  • Notice of Construction - Beck Road Bridge Replacement

    Description

    The City of Niagara Falls will be completing the reconstruction of Beck Road Bridge over Lyon’s Creek.
    Beck Road at Lyon’s Creek will be closed for the duration of construction. A signed detour will be setup along Marshall Road, Stanley Avenue, Rexinger Road, and Lyon’s Creek Road. In accordance with the contract documents, the contractor, Rankin Construction Inc. is required to notify emergency services of their daily operations.
    The work is scheduled to commence on December 4, 2023 and will be continuous until completion, approximately July 2024 weather permitting.

    For further information you may contact:
    Eric Lallouet
    Senior Project Manager
    Municipal Works
    City of Niagara Falls
    4310 Queen Street, P.O. Box 1023
    Niagara Falls, ON L2E 6X5
    (905) 356-7521 ext. 4216
    [email protected]

    Attachments

    Posting Dates

    12/1/2023 to 7/30/2024
  • QEW Burlington Skyway Southbound Lane Structural Rehabilitations & NB and SB Electrical Work (GWP 2385-15-00)

    Description

    The Ontario Ministry of Transportation (MTO) has retained WSP Canada Inc. (WSP) to undertake the Detail Design and Class Environmental Assessment Study (Class EA) for the structural rehabilitations of the Queen Elizabeth Way (QEW) Burlington Skyway southbound lane and the completion of electrical work on both the northbound and southbound QEW, within the City of Hamilton
    and the City of Burlington.

    The Burlington Skyway Niagara Bound structure will be rehabilitated in three main stages with all four lanes maintained during daytime and nightly lane closures as required. During each stage there will be single lane closures on the QEW throughout the weekends (Friday Night to Monday morning, approximately eight weekends per construction season) to rehabilitate the middle portions of the deck. Three lanes will be maintained over the Skyway structure during these weekend lane closures. Construction is expected to last for 3 years, and is anticipated to start in Spring 2024 with completion by Fall 2026.

    Please note that www.511on.ca is also a great resource for travel, construction/maintenance closures and activities on the provincial highways.

    If you wish to obtain additional information or provide comments, please contact one of the Project Team members listed below:

    Ben Hui, P.Eng., M. Eng.

    Senior Project Manager - WSP Canada Inc.

    6925 Cenury Ave, Floor 6,

    Mississauga, ON L5N 7K2

    Tel: 289-835-2506

    e-mail: [email protected]

    Alice Kam. P.Eng

    Senior Project Manager

    Ontario Ministry of Transportation

    159 Sir William Hearst Ave. 4th Floor

    Downsview, ON M3M 0B7

    Tel: 437-227-5587

    e-mail: [email protected]

    Attachments

    Posting Dates

    10/23/2023 to 10/23/2026
  • Road Widening and Reconstruction of Montrose Road (Regional Road 98), Lyons Creek Road (Regional Road 47) and Biggar Road in the City of Niagara Falls

    Description

    Please be advised that the Niagara Region and City of Niagara Falls will be widening and reconstructing the following roads in the City of Niagara Falls under Contract No. 2021-T-269:

    *Montrose Road (Regional Road 98) from Grassy Brook Road to 450m South of Lyons Creek Road (Regional Road 47)
    * Lyons Creek Road (Regional Road 47) from Willodell Road to Montrose Road (Regional Road 98)
    * Biggar Road from Montrose Road (Regional Road 98) to 850m West


    This contract will be carried out on behalf of Niagara Region and City of Niagara Falls by Beam-Rankin Joint Venture Ltd. Construction is tentatively scheduled to begin in the coming weeks. Construction is anticipated to be completed by July 2024, weather permitting. The consulting engineer, Parsons Inc., has also been retained to provide construction inspection and administration services.

    Residents are advised to visit the Niagara Region’s website niagararegion.ca/projects/montrose-lyons-creek-ea for upcoming project updates, road closures and related detour routes.

    Your patience and co-operation throughout this project is appreciated.

    Attachments

      Posting Dates

      3/15/2023 to 7/31/2024
    • Notice of construction for Niagara Falls Wastewater Treatment Plant

      Description

      Work is being done by Niagara Region at the Niagara Falls Wastewater Treatment Plant located at 3450 Stanley Avenue in Niagara Falls. This work is required to ensure continuous service in the future and includes: construction of new secondary (biological) treatment, including a new moving bed biofilm reactor treatment and aeration blower system and building, and a new chlorine contact tank and channel, upgrades to the grit system, primary clarifiers, secondary clarifiers, chemical system, substation and emergency power systems, and demolition of the existing secondary treatment.

      When: March 2022 - June 2024 

      During construction you may experience short-term interruptions along Stanley Avenue for new service connections and equipment deliveries. You may also experience noise from construction traffic on-site and pile driving required for the new tanks and buildings. Niagara Region will take all necessary measures to reduce the noise for nearby properties. 

      Contacts:

      Ian Trapnell, Site Superintendent
      Maple Reinders
      647-241-4376 

      Jared Rubinoff, Project Manager
      Maple Reinders
      416-994-8094 

      Lisa Vespi, Manager, Capital Projects
      Niagara Region
      289-929-4986 

      Attachments

        Posting Dates

        3/29/2022 to 6/30/2024